At Bayside Financial, where you work as a project manager, you have been asked to conduct user training sessions for a new information system. You must develop a specific schedule for the tasks (the estimated task duration for each is shown in parentheses):
First, confirm arrangements for the training facility you plan to use (3 days).
After you have confirmed the training facility, two tasks can begin at the same time: you need to send an e-mail message to all department managers announcing the training sessions (1 day) and you can develop the training material (5 days).
As soon as the training material is complete, you can work on two tasks at once: arrange to have copies of handout material printed (2 days) and develop a set of PowerPoint slides (5 days).
When the PowerPoint slides are ready, you conduct a practice training session with the instructor who will assist you (2 days).
Finally, when the practice session is over and the handout material is ready, you can conduct the user training sessions (4 days).
Tasks
Prepare a list showing all tasks and their durations.
Analyze the fact situation carefully to determine which tasks are concurrent and which ones are dependent on other tasks.
Create a Gantt chart that shows the project. Use a format similar to the one demonstrated on class.
What is the critical path for this project? How do you know?